Thursday, October 9, 2008

Cabin update

Ok, we now have a deadline to be done and closed on by the 13th of december. I have scheduled the carpet for the end of october. I sided the boat house most of the way. I wains coated and finished the lower staircase. I trimmed out both bedrooms and the main bathroom. I need to finish the tile work and grout. then I will start the hardwood in the loft and the main floor. It is all 3/4'' pre finished oak. There is a very nice contrast between the darker oak and the natural pine trim. Things are starting to come togeather. I finished the outside of the house, all that remains is the paint. My biggest challange that lies ahead is to build the costom oak steaircase up to the loft. I will post new picts soon.